














Here we are and it’s Day 8 of our conservatory re-build and we have been really lucky with the weather since the works started. The only rain, so far, has had the decency to hold off until the end of the working day. Sprinkling while the guys have been packing up. Seems our luck has run out and this morning is starting out dull, with a light drizzle, a condition I like to describe as drismal. So it’s on with the jackets for Bob and Simon, the brickies, suitably fortified with a hot cup of tea.
So I have been pondering the economics of home construction work and have come to realise that an essential item has been missed from our costing.
Tea !!!
Or rather I should say Tea, Milk and Sugar. It seems the great british workman is fuelled by sweet tea.
During a normal week we consume perhaps 30 – 40 tea bags, 1 – 1.5 pints of milk and no sugar assuming no sweet toothed visitors.
However, consumption has ramped up significantly and seems to be running at around 64 tea bags, 3 pints of milk and around 500 grams of sugar. This is just a rough guesstimate as the number of bods on site fluctuates. There is just the two of us but the workers vary from two to four and all but one drink their tea in the “white with two sugars” mix hence the sugar explosion.
And so I issue a word or two of advice to those considering a significant construction project on their own back door…..
If you want to keep them sweet, don’t forget to factor in the costs of providing regular teas to your workers.
What a difference a day makes……





Not much to report for yesterdays progress. The brickwork at the utility room end is up to the level where the new back door will be fitted.


At the opposite end, adjacent to the back door where the old conservatory had pulled the bungalow brickwork out of the vertical, repair work is almost complete.

The repairs would have been completed, were it not for the super hard screws used to secure the bedroom window. There were two and they seemed impervious to both of my hack saws, even with new blades fitted. Craig arrived early this morning and made short work of the screws using a mini disc cutter.
In the picture you can see that two different types of bricks are being used. Those nearest the door will not be seen when work is finished as the interior walls are being plastered. For those nearest the window frame and down they are reusing the original bricks as they are exterior to the conservatory and will be visible.

This picture shows how Barratt Homes fit doors in timber frame houses. Obviously it is robust enough but to my untrained eye it seems a little flimsy. After all it is plastic, not metal.
Bob and Anton are back this morning and are now, much to everyone’s surprise, to be assisted by Simon, another bricky. So the brickwork should progress quite nicely.
Here are just a few pictures to show progress so far. Nothing much to say as the day was event free. The guys just got on and laid bricks and blocks.



We had a sprinkling of rain towards the end of the day, thankfully not enough to stop work. By close of play yesterday they were up to the DPC.
Apparently, todays main task is the end wall which is full height cavity with no doors or windows to break up the brick runs.
More later.
After a well-earned weekend break the team from Executive are back on site and working. Gone are Anton and Angus, replaced by Bob and Connor. Still under the watchful eye of Craig.
I’ll say one thing for these guys, they arrive early and get underway pretty soon after, allowing for the time obviously. No machines until 08:00.
Starting today is the base brickwork, so compressor and pneumatic drill were picked up around 07:00 and shortly after cement mixer and barrows were delivered.
I’ll post pictures later today when there is something to see.
Day four and the guys have worked really hard. A little bit of hand digging to finish off the footings trench then it was on to preparing the steel reinforcements.

The picture above also shows the first barrow load of concrete poured into the trench.

The guys had to barrow all the concrete round from the front of the house to the back.

Two deliveries later and the footings were complete…

In between concrete deliveries the grab truck returned to remove the last of the spoil and the mini digger was collected and taken away. We have also had a delivery of bricks.
The guys now have a the weekend off. Back on Monday morning to start laying the brick base.